I move:
That Dáil Éireann:
notes that:
— climate change resulted in Irish temperatures in excess of 30°C in May, breaking a 29-year-old record by more than two degrees;
— a United Nations report has described Ireland as a cautionary tale on the environmental impact of data centres;
— the Government is implementing policies that will increase fossil fuel use, by facilitating further new data centres through the Commission for Regulation of Utilities (CRU) Large Energy User (LEU) connection policy, the introduction of private wires legislation, and the construction of a floating terminal for the importation and storage of liquid natural gas, including fracked gas;
— over 22 per cent of our electricity is already used by data centres, this will rise to over 30 per cent by 2030, and to 55 per cent if growth continues as projected, using more power than every other electricity user in the country combined;
— in May, the Climate Change Advisory Council noted that all new renewable energy being developed in the State is being cannibalised by new demand created by data centres, rather than going towards decarbonising homes, transport or industry;
— research projects that the 5.8 gigawatt (GW) of additional data centre capacity under the LEU may result in a doubling of the State's peak demand for electricity generation, and lead to an increase in gas consumption by 2030 against the current projected decline, should capacity be constructed ahead of new renewables capacity; and
— no offshore wind power generation capacity will be available before 2030 despite a 5 GW target;
further notes that:
— Ireland has the highest electricity prices in the European Union, and over 500,000 households are in arrears on their energy bills;
— the increased and inflexible energy demands of data centres means that more and more often gas generation sets the wholesale price of electricity, rather than renewables, resulting in higher prices for households, while Eurostat shows that large energy users pay lower network charges;
— research by Friends of the Earth Ireland, shows that Irish households paid an estimated €715 million more in electricity bills from 2015 to 2023 due to data centres, equivalent to €360 per household, and face an additional €1.43 billion in costs up to 2034, costing each household up to €644 more; and
— the Economic and Social Research Institute has shown that recent energy price increases hit low-income households harder, and that more targeted support measures are needed;
regrets that:
— the Climate Action Plan 2026 still has not been published;
— the final, phase 2 oversight group report of the Land Use Review, was submitted over a year ago and has still not been published; and
— planned legislation to prioritise critical infrastructure will bypass statutory climate obligations;
recognises that:
— data centres are essential infrastructure for the modern digital economy and the development of artificial intelligence technology but are overly concentrated in Ireland, are using an ever-increasing amount of energy, resulting in higher costs for households and businesses, and increased development is now at odds with our climate targets;
— discussion by Government of nuclear power is a nonsense and a form of climate obstructionism which distracts and blocks real climate action; and
— the Government will further increase carbon emissions by lifting the Dublin Airport cap, promoting unsustainable housing and economic development, and by no longer prioritising public transport and active travel investment over roads construction;
condemns the decision of the Government to use the Critical Infrastructure Bill 2026, to disapply Section 15 of the Climate Action and Low Carbon Development Acts 2015 to 2021 from designated projects; and
calls on the Government to:
— publish the Climate Action Plan 2026, and the final phase 2 oversight group report of the Land Use Review without any further delay;
— delete Section 7 of the Critical Infrastructure Bill 2026, and publish the legal advice confirming the constitutionality of the provision to disapply Section 15 of the Climate Action and Low Carbon Development Acts 2015 to 2021;
— suspend the CRU LEU connection policy, and commission an independent study of the impact of data centres on electricity prices, carbon emissions, water usage and grid stability;
— introduce a moratorium on the further construction of data centres until renewable energy from offshore wind comes online, and households and businesses can benefit from lower energy costs;
— introduce a levy on the energy usage of data centres, to recover the higher electricity costs now being imposed on Irish households and businesses;
— confirm by how much Ireland will miss our binding 2030 emission targets, what the cost of securing additional carbon credits will be, and how the next Government will pay for those; and
— immediately reintroduce targeted energy credits and more targeted Sustainable Energy Authority of Ireland supports for households in advance of Budget 2027.
We are bringing forward this motion today out of a genuinely held concern that this Government is giving up even the pretence of caring about our climate ambitions. Earlier this year, we had what felt like three months of non-stop rain, leading to severe flooding in parts of the country, including my constituency of Dublin South-West. Just a few weeks ago, Ireland recorded record temperatures above 30°C in May for the first time in almost three decades, shattering a record that had stood for 29 years by more than 2°C.
Speaking of breaking records, I increasingly feel like a broken record when I bring up our climate crisis in this House. In Ireland and globally, we are seeing much more frequent and severe weather events, from droughts to floods to extreme heat. We have moved beyond the point of warning about the potential consequences of climate change. It is here. These consequences are already being felt. Urgency is required to prevent the most catastrophic outcomes - urgency in bringing down our emissions, in our energy transition and in addressing the costs of this perpetual fossil fuel crisis.
However, this Government is failing to acknowledge that there is any urgency. It still has not yet published a climate action plan for this year. It is June. It has failed to publish the land use review, which has been sitting on the Minister's desk for over a year now. The Minister, who is not here, is trying to make a virtue of admitting that we are going to fail miserably in reaching our 2030 carbon reduction targets. What is another few years? This Minister will be long gone from the climate brief by the time any of this matters.
Not only is this Government failing to act with any real urgency to decarbonise; it is also actively pursuing policies that are moving us in the opposite direction. This motion seeks to address some of this Government's failings when it comes to climate, starting with the most obvious example - the rapid expansion of data centres and the consequences their growth is having on our climate obligations and on household energy bills.
None of us here are Luddites. We accept and understand that data centres are part of a modern economy and industrial strategy. We all have a mobile phone; we all use cloud services. Many of us even use artificial intelligence, AI, though certainly not for parliamentary questions. This is not a question about whether data centres should or should not exist, and I hope the Government does not try to reduce the debate to those binary terms again. The debate has moved on. The question is whether we are content to continue to allow unlimited expansion of these data centres without regard for the very real consequences on people and our environment. This is a question of the Government's industrial and economic strategy as much as it is a question of our climate obligations and the cost-of-living implications of this strategy. The Government must be honest about the consequences and costs of allowing more and more of our energy to be used by data centres. It must be honest that much of the legislation it is pushing through is designed to facilitate and placate large energy users. I refer to the private wires Bill, the strategic liquefied natural gas, LNG, emergency reserve, which will import highly polluting fracked gas, and the Commission for Regulation of Utilities, CRU's, new large energy user policy. Who knows what kinds of fossil fuel-guzzling projects a future Minister might deem to be critical infrastructure if that particular Bill passes?
The UN has described Ireland as a cautionary tale regarding the environmental impact of data centres. I would hope that would be a wake-up call for the Government but I will not hold my breath. Perhaps the Friends of the Earth report published a couple of weeks ago will be more impactful. It concluded that €715 million had been added to household bills between 2015 and 2023 as a direct result of data centre energy demands pushing up prices. A further €1.5 billion could be the price households pay for data centres over the next decade. This is at a time when, according to the latest figures from the CRU, more than 500,000 households are in arrears and cannot afford to keep up with their energy bills. We already have the highest electricity prices in the EU and this is, in part, directly attributable to data centres.
As our motion says, the massive energy demand from data centres means that gas is setting the wholesale price rather than renewables, making everyone's electricity more expensive. This is only going to get worse if we continue to build more and more of them. Data centres currently consume 22% of the electricity in this State. This is projected to grow to 30% by 2030 and they could ultimately consume as much as 55% of all the electricity demand in Ireland. This is insane. That is more than every household, school, hospital, small business, farm and factory combined. An entire energy system is increasingly organised around the demands of a small number of large corporate users and their interests.
That is why we are calling for the introduction of a levy on data centre energy usage. It is about fairness. Not alone are data centres pushing up prices for everyone else but we have a ludicrous situation where they are actually paying less than your average punter in network tariffs. If data centres are contributing to higher costs across the electricity network, then it is reasonable that they should contribute more towards those costs. It is not about punishing data centre operators or deterring investment. It is simply about making sure that ordinary households are not left footing the bill, which is currently the case.
What is particularly alarming is that the Climate Change Advisory Council has warned that all new renewable energy is being cannibalised by the growth in demand from data centres rather than decarbonising out transport sector, agriculture, industry or home heating. The Government's response to all of this has basically been, "Yeah, but jobs". However, the recent KPMG report commissioned by the Government makes the absolutely laughable claim that 900,000 jobs are attributable to data centres. The actual number of jobs directly created by data centres is around 19,500, the vast majority of which are in construction and are temporary in nature. The actual figure is about 3,000 ongoing jobs. That is not to be sniffed at, but is it worth building an entire energy system around and dumping our climate targets for? I would say the jury is out on that one.
The Government will say it is encouraging more renewables because 80% of the energy for our new data centres must come from renewables, but even with that, the remaining 20% will lead to a potential doubling of our peak gas demand. This means more imported fossil fuels, more emissions, more exposure to international energy price shocks and, ultimately, higher bills for hard-pressed Irish households. That is why we are calling for a moratorium on further data centre expansion. We want a pause until we have sufficient renewable capacity so we can ensure they are not impacting on our decarbonisation efforts or pushing up prices for ordinary households.
An additional concern addressed in our motion is the Government's Critical Infrastructure Bill and the disapplication of section 15 of the climate Act. Of course we want to see Ireland's infrastructure deficit filled. We have had a decade of wasted prosperity under Fine Gael and Fianna Fáil Governments and it is typical that they would now seek to point the finger for their failures to build our necessary infrastructure at anyone but themselves.
They are punching down on the environment. However, we need to be clear that seeking to uphold our environmental and biodiversity laws is not the cause of the delays in getting vital infrastructure built in a timely fashion in this country. It is resourcing issues. For years, our planning authorities, courts and public bodies have been under-resourced. That is the reason we are seeing decisions taking years and years, delaying delivery. That is not the fault of environmental law. It is a fault of Fine Gael's and Fianna Fáil's lack of strategic planning. None of the 20 delays to the completion of the National Children's Hospital is due to the environment. Section 15 of the climate Act exists for a reason. It ensures that our public bodies act consistently with our climate objectives. Removing it suggests that those objectives apply only when it is convenient and can be set aside when it is politically inconvenient. I will continue on this later.