I propose to take Questions Nos. 71 to 73, inclusive, 76, and 78 to 80, inclusive, together.
The information requested by the Deputy is provided in the following table.
|
Flood Relief Scheme
|
Current Stage
|
Expected date for Project to go to tender for construction*
|
Expected date for Construction commencement*
|
Expected date for Construction completion
|
Estimated total project cost**
€m
|
Expenditure to date
€m
|
|
Clonakilty
|
Construction (Commenced Q2 2018)
|
N/A
|
N/A
|
Q2 2020
|
€24.1
|
€14.2
|
|
Bandon
|
Substantially Complete
|
N/A
|
N/A
|
Q3 2020
|
€28.4
|
€24.2
|
|
Lower Lee (Cork City)
|
Detailed design
|
Mid to late 2020
|
2021
|
Anticipated construction period of 5-6 years
|
€140m (currently under review to take account of design changes since Public Exhibition)
|
Approx €9m. (this includes Site Investigation works, surveys, Consultants’ fees and Invasive Species treatment)
|
|
Bray
|
Complete
|
N/A
|
N/A
|
Complete
|
€43
|
€42.6
|
|
Arklow
|
Design
|
2021
|
2021
|
2023
|
€28
|
€0.9
|
|
Enniscorthy
|
Detailed Design
|
2020
|
2020
|
2023
|
€44.5
|
€3.57
|
|
Skibbereen
|
Substantially complete
|
N/A
|
N/A
|
Q4 2019
|
€34.5
|
€25.4
|
* Dates given for projects to go to tender and for construction commencement are best estimates at this stage and are subject to planning approval or Ministerial Confirmation
**These are current best estimates of cost based on information available at this time and are subject to change.