My Department fully supports Dublin City Councils refurbishment or rebuild of social housing complexes in Dublin 8, 10, and 12.
The aim of a regeneration project is to create sustainable communities through a combination of social, educational and economic initiatives and also by rejuvenating the built environment by a mixture of demolition, construction and refurbishment of dwellings having regard to urban design guidelines.
The following programmes have been approved for funding and I am advised of the following completion dates by Dublin City Council.
|
Scheme
|
Location
|
Project Name
|
Projected Completion
|
|
DCC
|
Dublin 8
|
Dolphin House, phase 1 b
|
Q4 2027
|
|
DCC
|
Dublin 8
|
School Street, Thomas Court Bawn phase 1
|
Q3 2027
|
|
DCC
|
Dublin 8
|
School Street, Thomas Court Bawn phase 2
|
Q1 2029
|
|
DCC
|
Dublin 8
|
Emmet Road, phase 1
|
Q4 2027
|
|
DCC
|
Dublin 8
|
Emmet Road, phase 2
|
Q1 2028
|
|
DCC
|
Dublin 8
|
Emmet Road, phase 3
|
Q2 2028
|
|
DCC
|
Dublin 8
|
Oliver Bond House
|
Q1 2029
|
|
LDA
|
Dublin 8
|
Donore Project
|
Q4 2027
|
|
LDA
|
Dublin 10
|
Cherry Orchard Point
|
Q4 2029
|
|
LDA
|
Dublin 12
|
Bluebell Waterways
|
Q4 2029
|