213. Deputy Cathal Crowe asked the Minister for Public Expenditure, National Development Plan Delivery and Reform if he will provide an update on preparatory works being undertaken by the Office of Public Works in order that a new building for a school (details supplied) can progress; and if he will make a statement on the matter. [24826/24]

View answer

Written answers

The Office of Public Works (OPW) is nearing completion of the detail design for the main school works at Knockanean National School, Co. Clare.  It is expected that the OPW will be in a position to submit the Stage 2B report to the Department of Education at the end of July 2024.  If the Department accepts the report the OPW will then proceed with the tender process for the main works.