Dáil Éireann Debate, Wednesday - 10 July 2024

Wednesday, 10 July 2024

Questions (98)

Thomas Gould

Question:

98. Deputy Thomas Gould asked the Minister for Education the number of applications received from schools in Cork under the major capital works scheme; and the number granted to date in 2024, in tabular form. [30186/24]

View answer

Written answers

As requested by the Deputy, please see attached table showing projects for schools in Cork which received initial approval in 2024.

Please note that there are other school building projects in Co Cork at various stages of progress. The Department's website provides a list, by county, of all projects being progressed under the large scale and additional accommodation scheme. This is available here: gov - Building works for the construction, extension and refurbishment of schools (www.gov.ie) .

The stage of architectural planning is included for each project on the website. The following provides a summary of what is involved at each stage:Stage 1 – Preliminary Design. The Preliminary Design stage includes reviewing all information provided as part of the Project Brief, establishing and analysing all site factors and constraints which may impact on the project's viability.Stage 2 - Design (which is divided into Stage 2a - Developed Sketch Scheme and Stage 2b - Detailed Design)

Stage 2a includes developing the design and accurately cost planning the options agreed with the Client to a stage where the project is fully cost planned and can be prepared to lodge for statutory approvals.Stage 2b includes obtaining all statutory approvals, preparing a set of fully detailed tender documents, and preparing an accurate pre-tender cost plan.Stage 3 - Tender Action, Evaluation and Award is the procurement stage, which includes the implementation of the tender process, evaluation of tenders and award of the contract.

Stage 4 – Construction refers to the period during which the construction works are delivered on site. All members of the Design Team are collectively responsible for the effective management of the project in order to achieve its completion on time and within budget. Stage 5 - Handover of Works and Final Account refers to the final stages of project close-out, after works have been completed.

Roll Number

School_Planning_Area

School Name

Address_2

Year Approved

Total_Project_Brief

Programme List

Current_Stage_Of_Project

81008W

Ballintemple_CorkCity

Ashton School

Cork

2024

Science lab & prep area 1x Art room 1x Graphics room: 4x Special education classroom 1x music room: 1x Mainstream classroom: reconfiguration of smaller GP room as fitness suite

Additional School Accommodation Scheme

Stage 1

20574O

Midleton_Carrigtwohill

East Cork Community National School

Cork

2024

Reconfiguration works to existing accommodation to provide SEN classrooms are being reconfigured from spare classrooms in the new Carrigtwohill Community NS RN 20442U.

Additional School Accommodation Scheme

Stage 5

20006A

Clonakilty

Gaelscoil Mhichíl Uí Choileáin

Cloch na gCoillte

2024

Soft play area for existing 4 x SEN

Additional School Accommodation Scheme

Stage 2b

91391H

Passage West

St Peter's Community School

Co Cork

2024

Reconfiguration of Music room for SEN Class

Additional School Accommodation Scheme

Stage 5

20534C

Carrigaline

Owenabue ETNS

Heron's Wood

2024

reconfiguration of old retail unit to provide 2 x MCR and multipurpose room.

Additional School Accommodation Scheme

Stage 3

14839P

Macroom

CLONDROHID N S

Macroom

2024

1x SEN reconfiguration

Additional School Accommodation Scheme

Stage 1

81009B

Boharbue

Boherbue Comprehensive School

Boherbue

2024

Reconfiguration to provide Sensory Room for 4 existing Special Education Needs classrooms

Additional School Accommodation Scheme

Stage 4

70960D

Coachford

Coachford College

Co Cork

2024

Reconfiguration of classroom to provide SEN classroom

Additional School Accommodation Scheme

Stage 4

62061T

Bandon

Coláiste na Toirbhirte

Bandon

2024

2 x 100m2 Modular Classrooms SEN Classrooms

Additional School Accommodation Scheme

Stage 1

62580U

Glasheen_CorkCity

Coláiste an Spioraid Naoimh

Cork

2024

Reconfiguration to provide interim 1x Special Education classroom

Additional School Accommodation Scheme

Stage 4

11262R

Rath Luirc_Charleville

DRUIMNE N S

Charleville

2024

1x MCR reconfiguration of prefab for class displaced by SEN class

Additional School Accommodation Scheme

Stage 3

62730N

Montenotte_CorkCity

St Patricks College

Cork

2024

Phase 1 - Reconfiguration of part of main building to provide 1 x Technology Room/Prep Area and Toilets to facilitate school going co-educational from 2024/25

Additional School Accommodation Scheme

Stage 1

76090G

Bantry

Coláiste Pobail Bheanntraí

BANTRY

2024

Reconfiguration of meeting room/offices to create 1x Special Education classroom and reconfiguration for displaced meeting room/offices

Additional School Accommodation Scheme

Stage 1

62170B

Clonakilty

Sacred Heart Secondary School

Clonakilty

2024

reconfiguration of existing space to be utilised for a second sen class

Additional School Accommodation Scheme

Project Brief

12292I

Coachford

CANOVEE MIXED N S

Macroom

2024

Reconfiguration for 1x Special Education classroom

Additional School Accommodation Scheme

Project Brief

15594Q

Fermoy

GRANGE FERMOY N S

Fermoy

2024

Reconfiguration of mainstream classroom to provide 1x Special education classroom

Additional School Accommodation Scheme

Stage 1

62693K

Glasheen_CorkCity

Presentation Secondary School

Ballyphehane

2024

Reconfiguration of toilets for change to co-ed

Additional School Accommodation Scheme

Stage 2b

62170B

Clonakilty

Sacred Heart Secondary School

Clonakilty

2024

Reconfiguration of MCR for SEN Provision

Additional School Accommodation Scheme

Stage 1