The Project referred to by the Deputy was approved to enter the department’s pipeline of school buildings in June 2021 to provide a four Classroom Special Educational Needs (SEN) base, a General purpose room and Ancillary under the department‘s Additional School Accommodation (ASA) Scheme. The project has been devolved for delivery to the school authority.
I can confirm that this project received my departments approval to go to planning in Q1 of 2024 and the department awaits a post planning (developed design) report from the school for review.
The delays have been primarily due to the timing required for the appointment of a design team, the subsequent development of the design and the necessary review of the project from both a technical and cost perspective in accordance with the requirements of the Public Spending Code.
My department will continue to engage with the school authority to provide practical advice and assistance on this much needed project. It is now within the remit of the school authority to progress this project accordingly.