My Department works collaboratively, through SOLAS and the HEA, with the Education Training Boards and all higher education institutions on the development and delivery of capital projects.
Capital investment in Carlow and Kilkenny for 2024 will be realised through existing capital projects and devolved funding mechanisms as detailed in the below table.
The table below outlines Further Education and Training (FET) and Higher Education (HE) projects currently in train throughout counties Carlow and Kilkenny.
|
Programme
|
County
|
Institute
|
Project
|
Status
|
|
|
|
|
|
|
|
FET: Strategic Infrastructure Upgrade Fund
|
Kilkenny
|
Grennan Equestrian Centre, Thomastown, Kilkenny Carlow ETB
|
Project to replace existing temporary accommodation
|
Project is currently at an advanced stage of architectural planning
|
|
FET: College of the Future Major Projects Fund
|
Kilkenny
|
Kilkenny Carlow ETB
|
FET College of the Future
|
Kilkenny Carlow ETB have submitted a proposal under the FET College of the Future Major Projects Fund to develop a flagship facility on a new site in Kilkenny. The business case for their proposal is currently being evaluated and this process is expected to conclude in the coming weeks. In parallel, work continues advancing the acquisition of an appropriate site for the college.
|
|
FET: Apprenticeship Fund
|
Kilkenny
|
Training Centre – Purcellsinch Training Centre, Kilkenny Carlow ETB
|
Refurbishment Works to provide 2 x electrical workshops and classroom / training room
|
Works valued at approximately €1.9m were completed in August 2024
|
|
FET: Devolved Capital Grant
|
Kilkenny & Carlow
|
Kilkenny Carlow ETB
|
Devolved capital funding managed by the ETB
|
€435,000 annual allocation for KCETB for 2024 Flexible funding to support ETBs with small-scale building works and equipment purchase or renewal
|
|
HE: Energy Efficiency Decarbonisation Pathfinder Programme (EEDPP) 2021
|
Carlow
|
SETU Carlow Campus
|
Burrin Building - Medium retrofit with high-temperature air source heat pump
|
On Site – Expected Completion due in Q4 2024
|
|
HE: PPP Programme Bundle 2
|
Carlow
|
SETU Carlow
|
Science and Health Building
|
The final tender for Bundle 2 was received in March 2024 and construction is expected to commence in Q1 2025 - subject to Cabinet approval
|