Dáil Éireann Debate, Thursday - 19 September 2024

Thursday, 19 September 2024

Questions (75)

Pauline Tully

Question:

75. Deputy Pauline Tully asked the Minister for Housing, Local Government and Heritage the actions he has taken to reduce the housing waiting list in Cavan; and if he will make a statement on the matter. [36994/24]

View answer

Written answers

Housing for All is the Government’s plan to increase the supply of housing to an average of 33,000 per year over the next decade. This includes an average of 10,000 new build social homes each year in the period to 2030. Housing for All is supported by an investment package of over €4bn per annum, through an overall combination of €12bn in direct Exchequer funding, €3.5bn in funding through the Land Development Agency and €5bn funding through the Housing Finance Agency.

Under Housing for All, the Government will deliver 47,600 new build social homes; 3,500 social homes through long-term leasing and 28,500 new affordable homes in the period 2022-2026. Increased delivery of social housing is a key Housing for All objective and is supported through a range of funding streams delivered via local authorities and Approved Housing Bodies (AHBs). The number of completed new build social homes, and the number in the pipeline, continues to grow year-on-year, with new construction projects added to the pipeline regularly.

Housing for All required each local authority to prepare a Housing Delivery Action Plan to address social and affordable housing needs in their areas over the period 2022-2026, in line with targets set under Housing for All. The Plans include details of planned local authority, AHB and Part V delivery for social housing schemes. The Plans do not include additional affordable homes that will be delivered by the LDA, AHBs, First Home and via the higher Part V requirements introduced in the Affordable Housing Act 2021. A copy of each local authority's Housing Delivery Action Plan is available on their websites.

My Department publishes the Social Housing Construction Status Report (CSR). The CSR provides details of social housing developments and their location that have been completed, are under construction or are progressing through the various stages of the design and tender processes.

The most recent publication was for Quarter 1 2024. All Construction Status Reports are available at the following link: www.gov.ie/en/collection/cb885-social-housing-construction-projects-status-reports/

A version of the CSR file can also be downloaded for analysis by local authority at the link below: www.gov.ie/en/publication/cbe5c-social-housing-construction-projects-status-report-q1-2024/