I propose to take Questions Nos. 76 and 80 together.
The large scale capital project for the schools referred to by the Deputy, is included in my Department’s construction programme which will be delivered under the National Development Plan (NDP) as part of Project Ireland 2040.
The project brief for the schools Campus, includes the phased construction of two 16 classroom primary schools with a PE hall for the post primary school.
The project is at Architectural Planning Stage 4 - Construction.
Works commenced on site in September 2024 with an estimated contract duration of 20 months.