647. Deputy Edward Timmins asked the Minister for Education when she will sanction the next stage of the building project in a school (details supplied). [1838/25]

View answer

Written answers

The project referred to by the Deputy has been devolved to the National Development Finance Agency (NDFA) for delivery as part of a programme of school building projects.

The project is currently at Stage 2b, with a full grant of planning permission received for the school. The NDFA’s Design Team is working to conclude the pre-tender stage in conjunction with the Department. When Stage 2b has been finalised and approved, the next stage is tendering for a contractor and then onwards to construction in due course.

While at this early stage, it is not possible to provide a timeline for the completion of the project. The NDFA will continue to engage directly with the school authorities to keep them informed of progress.

The current status of all projects is listed on a county by county basis at www.gov.ie. and this is updated on a regular basis to reflect project progress through the various stages of capital appraisal, site acquisition, design, tender and construction.