Questions (302)

Tom Brabazon

Question:

302. Deputy Tom Brabazon asked the Minister for Public Expenditure, National Development Plan Delivery and Reform the refurbishment works that the OPW has scheduled to carry out at Coolock Garda station for the remainder of 2025; and when each of those refurbishment works projects will commence, in tabular form. [13996/25]

View answer

Written answers

I can confirm that the Office of Public Works has scheduled refurbishment works to Coolock Garda Station, to be carried out in 2025 as outlined in the table below.

The commencement/completion dates for the scheduled works are subject to the final sign-off of operational and design requirements by An Garda Síochána.

Garda Station

Nature of works

Commencement Date

Coolock.

Universal Access Works - comprising works to the external entrance ramp and steps, and public reception area.

Q2 2025.