Schools Refurbishment

Dáil Éireann Debate, Tuesday - 25 March 2025

Tuesday, 25 March 2025

Questions (384)

Darren O'Rourke

Question:

384. Deputy Darren O'Rourke asked the Minister for Education when her Department expects refurbishment works at a school (details supplied) to be completed. [13908/25]

View answer

Written answers

The project to which the Deputy refers is devolved for delivery to Waterford and Wexford Education and Training Board (WWETB).

The brief for this project comprises of the development of a new purpose-built, 25 classroom school for pupils with special educational needs.

The project is currently at Stage 3 (tender stage) of the architectural design process. The Design Team are currently following the procurement procedures for the appointment of the contractor for the project.

It is not possible at this juncture to give a definitive timeline for completion of the project. However, WWETB will continue to engage directly with the school authority to keep it informed of progress.