Dáil Éireann Debate, Tuesday - 1 April 2025

Tuesday, 1 April 2025

Questions (865)

John Paul O'Shea

Question:

865. Deputy John Paul O'Shea asked the Minister for Rural and Community Development the funding allocated to Cork County projects as part of the local improvement scheme from 2020 to 2024; the projects approved; the monies for same that have been drawn down by Cork County Council, in tabular form; and if he will make a statement on the matter. [15169/25]

View answer

Written answers

The Local Improvement Scheme (LIS) supports improving non-public rural roads and laneways not usually maintained by local authorities. Since its establishment in 2017, almost €170 million has been provided by the Government to local authorities for LIS. Given LIS is intended to support the upkeep of rural roads, Cork City Council does not form part of the scheme.

In April 2024, €40 million in funding was announced for LIS across local authorities to cover 2024/2025. My officials have recently opened the administration of the 2025 Local Improvement Scheme.

Since 2017, Cork County Council has been allocated a total of €12.99 million in funding. This figure includes the 2024/2025 allocation of €2.87 million.

While my Department provides funding to local authorities to support the operation of the scheme, each local authority is solely responsible for the prioritisation and selection of roads for inclusion in the scheme. Applicants apply directly to the Council and provide a local contribution towards the works and as such, the records of individual applicants and projects are maintained at local authority level.

The table below displays the information requested by the Deputy from 2020 – 2024.

Year

Allocation

Drawdown

Roads Completed

2020

€900,000

€896,693

19

2021

€1,412,738

€1,410,172

29

2022

€1,298,240

€1,173,997

22

2023

€2,755,923

€2,580,961

47

2024/2025

€2,868,444

€1,618,457 (2024)

31 (2024 total)

Total

€9,235,345

€7,680,280

148

Share