Question:66. Deputy Darren O'Rourke asked the Minister for Education when her Department expects refurbishment works at a school (details supplied) to be completed. [21325/25]
View answerDáil Éireann Debate, Wednesday - 30 April 2025
66. Deputy Darren O'Rourke asked the Minister for Education when her Department expects refurbishment works at a school (details supplied) to be completed. [21325/25]
View answerThe project to which the Deputy refers has been devolved for delivery to Cavan and Monaghan Education and Training Board (CMETB).
This project is currently at Stage 4 which is the construction stage.
It is envisaged that the project will be substantially completed in quarter three 2025 in accordance with the April 2025 Progress report from CMETB.
My Department will continue to engage with CMETB to progress this important project, and CMETB will directly engage with the school to keep them informed throughout.