As the Deputy may be aware, the Cork Area Commuter Rail Programme is a key project in the National Development Plan 2021-2030 and the Cork Metropolitan Area Transport Strategy 2040. The Programme is being delivered on a phased basis and will provide a more efficient and decarbonised transport service for the area to help facilitate population and economic growth over the coming decades.
Phase 1 of the Programme consists of a signalling upgrade, construction of a through-platform at Kent Station, and double-tracking from Glounthaune to Midleton. This phase has received EU Funding under the National Recovery and Resilience Plan and is expected to be completed by the end of 2026.
Phase 2 of the programme plans for the electrification of the Cork commuter rail network and the delivery of up to eight new stations in the following locations: Tivoli, Dunkettle, Water Rock, Carrigtwohill West, Ballynoe, Blackpool / Kilbarry, Monard and Blarney/Stoneview. A public consultation is expected this Summer on the matter.
In 2024, Iarnród Éireann (IÉ) awarded a contract to TYPSA and Roughan O’Donovan appointing them as multi-disciplinary consultants for the design of Phase 2 of the Programme. This Phase provides for the new stations among other works.
Subject to securing funding and achieving the relevant approvals, Phase 2 of the Programme will progress after Phase 1 works have been completed.
Noting the NTA's responsibility in this matter and the specific issues raised by the Deputy, I have referred the Deputy's questions to the NTA for a more detailed reply. Please contact my private office if you do not receive a reply within 10 days.