Alan Kelly
Question:218. Deputy Alan Kelly asked the Minister for Public Expenditure, Infrastructure, Public Service Reform and Digitalisation to provide a list of all capital upgrades to Baltinglass Garda station since 2005. [35112/25]
View answerDáil Éireann Debate, Thursday - 26 June 2025
218. Deputy Alan Kelly asked the Minister for Public Expenditure, Infrastructure, Public Service Reform and Digitalisation to provide a list of all capital upgrades to Baltinglass Garda station since 2005. [35112/25]
View answerAn non-exhaustive list of capital upgrades to Baltinglass Garda station since 2018 is summarised in Table A below.
The information provided reflects what has been reasonably accessibly within the PQ response timeframe, it does not include paper-based information that has been archived.
Table A.
|
Description |
|
Cell Upgrade |
|
Conversion of Garage to Locker Room |
|
Security upgrade works |
|
Lights in canteen and office |
|
Installation of Power and data |
|
Preventative Maintenance |
|
Power and data for conversion of female changing room & Traffic Office |
|
Installation of AC in Comms Room |
|
Installation of Data Points to facilitate migration to VOIP Telephony |
|
Installation of Data Ports |
|
Installation of Power and Power Distribution Unit |
|
Installation of a Burco Boiler |
There are a number of capital upgrades to Baltinglass Garda station being progressed.
Details of these projects are summarized below in Table B.
|
Description |
Comment |
|
Kitchen and Bathroom Upgrade, Parking and Accessibility |
Currently at Tender preparation stage, anticipate contract award before the end of 2025. |
|
New Proposed kitchen at Baltinglass |
To progress after current Universal Access project above. |
Table B.