89. Deputy Paul Lawless asked the Minister for Housing, Local Government and Heritage if he will consider amending the defective concrete blocks grant scheme to include an additional allowance for the restoration of gardens that are destroyed during the demolition and reconstruction of affected homes; if he is aware that the average cost of garden restoration is estimated at between €8,000 and €13,000; if he will ensure homeowners are supported in fully restoring their homes, including outdoor spaces, rather than being left with a building site; and if he will make a statement on the matter. [52200/25]

View answer

Written answers

The Remediation of Dwellings Damaged by the Use of Defective Concrete Blocks Act 2022 (the Act) commenced on 22 June 2023 which contains the current grant scheme and the related Regulations were adopted on 29 June 2023.

My Department keeps costs relating to the DCB Scheme under continuous review. An increase in the scheme cap and rates was provided for in October and November 2024. These increases were made following the receipt and consideration of updated cost reports from the Society of Chartered Surveyors Ireland (SCSI) and advice from the Expert Group established to consider the matter.

The average rebuild costs include the costs for:

• Demolition and reconstruction costs.

• Concrete path around the house.

• Disconnection and reconnection of utilities.

• Making good to driveway and garden.

• Professional fees.

• VAT at 13.5% on building costs and 23% on professional fees.

The detailed implementation of the DCB Scheme is a matter for each designated local authority and queries related to individual properties should be directed to the relevant local authority.