Skip to main content
Normal View

Agriculture Schemes

Dáil Éireann Debate, Tuesday - 14 October 2025

Tuesday, 14 October 2025

Questions (748)

Pa Daly

Question:

748. Deputy Pa Daly asked the Minister for Agriculture, Food and the Marine the number of delayed ACRES payments, by county, and by average duration of delay; the reason for the delay; and if he will make a statement on the matter. [55354/25]

View answer

Written answers

The requested breakdown of figures per county is currently being compiled and will be forwarded directly to the Deputy on completion.

The following deferred reply was received under Standing Orders.
I wish to advise that a total of €697.55 million has been paid, to 17 November 2025, to participants in the Agri-Climate Rural Environment Scheme (ACRES) in respect of their participation in the Scheme.
The number of participants who are awaiting 2024 ACRES payment, by county, is shown in the table below.

County

Total

Carlow

2

Cavan

25

Clare

57

Cork

129

Donegal

95

Dublin

1

Galway

144

Kerry

91

Kildare

12

Kilkenny

9

Laois

9

Leitrim

37

Limerick

34

Longford

15

Louth

0

Mayo

156

Meath

10

Monaghan

5

Offaly

5

Roscommon

26

Sligo

21

Tipperary

44

Waterford

18

Westmeath

10

Wexford

23

Wicklow

16

994

The issues which have impacted on the making of payments are primarily:
• Contract and ownership / partnership issues such as requests for the transfer of contract following the date of the participant. Scheme payments where the original participant has died may not be progressed until the legalities such as probate are concluded,
• Issues with scorecards (incorrect score, scorecards not submitted, alignment of scorecards with data from the Basic Income Support for Sustainability Scheme (BISS)),
• Alignment of ACRES data with BISS information, and
• The non-submission to date by participants, or by their ACRES advisors on their behalf, of certain returns/information related to their application.
Given the range of reasons causing delays in the issue of payment, it is not possible to provide an average duration of delay.
My officials continue to examine all contracts, in respect of which payments remain to be issued, on an individual basis to ascertain the reason why they have not passed the required pre-payment validations, as well as the way in which the issue may be resolved to facilitate the issue of the payment to the participant concerned.
I trust that this information is satisfactory.