Louis O'Hara

Question:

135. Deputy Louis O'Hara asked the Minister for Education and Youth the measures being taken to reduce waiting times for school building projects in areas such as County Galway; and if she will make a statement on the matter. [69831/25]

View answer

Written answers

Since 2020, my department has invested over €6 billion in our schools throughout the country under the National Development Plan, involving the completion of over 1,300 school building projects. In addition, repurposing and optimisation of existing accommodation capacity across the school estate has been a key enabler of timely, local provision of special class capacity in a way that supports best practice in inclusion and integration. Circa 80% of new special classes in 2025/26 are being facilitated in repurposed classroom accommodation.

Government support for this investment, including by way of supplementary capital funding, has delivered real benefits for school communities. Supplementary capital funding of €210 million approved by Government has brought the total capital allocation for 2025 for my department to €1.6 billion.

In July the Government announced a capital allocation of €7.55 billion for the Department of Education and Youth for the period 2026-2030 under the National Development Plan. As part of this NDP allocation my department will place a strong emphasis on provision for children with special educational needs, with a particular focus on meeting annual school place needs. In relation to project rollout for Large-Scale projects and Additional School Accommodation scheme projects, the approach will be to continue to maximise the capacity of the existing school estate as much as possible in the first instance and provide necessary additional capacity through targeted and prioritised project rollout over the course of 2026 to 2030 period to meet the most urgent and prioritised needs.

My department will publish our sectoral NDP Implementation Plan shortly. This plan will optimise outputs from the NDP allocations, with a strong focus on maximising existing school capacity, progressing priority projects where local capacity across schools in the area is insufficient, and ensuring delivery that is affordable, offers value for money, and meets functional needs.

Delays can occur in large capital programmes for many reasons, including factors beyond my department’s control, such as the time taken to secure a site or securing relevant statutory permissions including planning consent. The Department also has to manage the rollout of projects within the parameters of its NDP funding.

Potential delays are managed as effectively as possible, prioritising the most urgent projects where capacity is already fully utilised, and deploying modular accommodation where additional space is needed in the short term.

My department has invested over €234m in capital expenditure since 2020 in Galway. This investment has supported the completion of 82 school building projects. Currently 22 projects are in construction, of which 1 is a new school building. In addition, 27 further projects are at an advanced stage of delivery, of which 7 are New School Buildings.

The current status of all projects is set out under item number ten at the following link [(www.gov.ie)]. ?This is updated on a regular basis to reflect project progress through the various stages of capital appraisal, site acquisition, design, tender and construction.?