Dáil Éireann Debate, Thursday - 11 December 2025

Thursday, 11 December 2025

Questions (406)

Séamus McGrath

Question:

406. Deputy Séamus McGrath asked the Minister for Education and Youth further to Parliamentary Question No. 993 of 8 September 2025, the position regarding the proposed building works at a school (details supplied). [70978/25]

View answer

Written answers

The school referred to by the Deputy was approved under the Additional School Accommodation Scheme to provide 1 mainstream classroom and a 2 classroom SEN base. The project is devolved to the school authority for delivery.

The project remains under careful review at Stage 2b due to the importance of compliance with costs under the public spending code. My Department will revert to the school as soon as this review is complete.

Since 2020, my department has invested over €6 billion in our schools throughout the country under the National Development Plan, involving the completion of over 1,300 school building projects. In addition, repurposing and optimisation of existing accommodation capacity across the school estate has been a key enabler of timely, local provision of special class capacity in a way that supports best practice in inclusion and integration. Circa 80% of new special classes in 2025/26 are being facilitated in repurposed classroom accommodation.

Government support for this investment, including by way of supplementary capital funding, has delivered real benefits for school communities. Supplementary capital funding of €210 million approved by Government has brought the total capital allocation for 2025 for my department to €1.6 billion.

In July the Government announced a capital allocation of €7.55 billion for the Department of Education and Youth for the period 2026-2030 under the National Development Plan. As part of this NDP allocation my department will place a strong emphasis on provision for children with special educational needs, with a particular focus on meeting annual school place needs. In relation to project rollout for Large-Scale projects and Additional School Accommodation scheme projects, the approach will be to continue to maximise the capacity of the existing school estate as much as possible in the first instance and provide necessary additional capacity through targeted and prioritised project rollout over the course of 2026 to 2030 period to meet the most urgent and prioritised needs.

Government departments are currently in the process of publishing their sectoral NDP Implementation Plans. The sectoral plan for the Education and Youth sector will be published next week and the first tranche of projects to progress to construction will be published in January. This NDP Implementation Plan will optimise outputs from the NDP allocations, with a strong focus on maximising existing school capacity, progressing priority projects where local capacity across schools in the area is insufficient, and ensuring delivery that is affordable, offers value for money, and meets functional needs.