The River Bride (Blackpool) Flood Relief Scheme was submitted for confirmation under the Arterial Drainage Act 1945 by the OPW in August 2018. In early 2021, the scheme received Ministerial confirmation under Section 7 of the Act. This decision was then subject to Judicial Review challenge, during which a stay was also granted on works being carried out pending the resolution of these proceedings.
Acting on legal advice, in early 2022, my Department conceded the matter on a single ground related to public consultation procedures as part of the confirmation process and consented to an order reverting the evaluation of the Blackpool Flood Relief scheme back to an earlier phase of the process.
A request for supplementary information was subsequently made to the OPW under section 7B(4) of the Act to which the OPW complied by supplying information in October 2022. Following an examination of all material provided to date, the environmental consultants retained by my Department recommended that a further supplementary information request be made to the OPW. This request was made to the OPW in November 2023 and the OPW have supplied further information to this effect, most recently in April 2025 and August 2025.
Following receipt of this information, a further period of public consultation was carried out as prescribed by the Act. This period of public consultation ended in October 2025 with over 1,000 submissions made to my Department. The submissions received are being examined by the environmental consultants retained by my Department which will inform next steps and associated timelines for consent process.