338. Deputy Emer Currie asked the Minister for Transport for an update on the underpass at Ashtown station following the recent NDP review; and if he will make a statement on the matter. [3964/26]

View answer

Written answers

As the Deputy may be aware, the National Transport Authority (NTA) has responsibility for the planning and development of public transport infrastructure in the Greater Dublin Area (GDA) including, in consultation with Iarnród Éireann, the DART+ programme.

The DART+ programme, which comprises five different projects in and around the GDA, will triple the length of the electrified network from circa 50km to 150km and double city centre capacity from 26,000 passengers per hour per direction to 52,000 during peak hours. This will significantly enhance access to high capacity public transport across the GDA.

DART+ West, which will serve Ashtown Station, will provide an extension of DART services from the City Centre to M3 Parkway and Maynooth, and the construction of a new depot and city centre enhancements.  

Conditional planning approval was granted for DART+ West in July 2024.  Procurement for DART+ West is progressing with pre-qualification questionnaires (PQQ) notices for Design and Build works advertised in May 2025. 

Funding secured under the NDP Sectoral Investment Plan, published by the Department of Transport in November 2025, will see construction start before 2030 on the DART+ programme, beginning with DART+ West, which is the crucial enabler of the rest of the programme.

Noting the NTA's responsibility in the matter, I have referred the Deputy's question to the NTA for a more detailed reply. Please contact my private office if you do not receive a reply within 10 days.

A referred reply was forwarded to the Deputy under Standing Orders.