School Accommodation

Dáil Éireann Debate, Tuesday - 20 January 2026

Tuesday, 20 January 2026

Questions (493)

Cathal Crowe

Question:

493. Deputy Cathal Crowe asked the Minister for Education and Youth when a school (details supplied) will hear the outcome of a report into the needs of the school; and if she will make a statement on the matter. [3489/26]

View answer

Written answers

The school to which the Deputy refers was approved to enter my Department's pipeline for a project under the Additional Schools Accommodation (ASA) scheme.

The project initially was approved to provide one science laboratory and preparation area, one technical graphics/DCG room, one technology preparation room, one construction studies room, one music room, one project store and ancillary. The school subsequently requested two additional mainstream classrooms to be added to the brief, which was approved by my Department.

The project was devolved for delivery to the school authority.

The Stage 2a (developed design) report outlining the proposed design and costings was submitted to the Department. This is currently under review from both a technical and cost perspective in accordance with the requirements of the Public Spending Code. Once the review is completed, the outcome will be communicated to the school authority to keep them fully informed of progress.

In July 2025, the Government announced a capital allocation of €7.55 billion for the Department of Education and Youth for the period 2026-2030 under the National Development Plan. As part of this NDP allocation the Department will place a strong emphasis on provision for children with special educational needs, with a particular focus on meeting annual school place needs. In relation to project rollout for Large-Scale projects and Additional School Accommodation scheme projects, the approach will be to continue to maximise the capacity of the existing school estate as much as possible in the first instance and provide necessary additional capacity through targeted and prioritised project rollout over the course of 2026 to 2030 period to meet the most urgent and prioritised needs.

The NDP Implementation Plan for the Education and Youth sector and the first tranche of projects to progress to construction will be published by the Department shortly. This NDP Implementation Plan will optimise outputs from the NDP allocations, with a strong focus on maximising existing school capacity, progressing priority projects where local capacity across schools in the area is insufficient, and ensuring delivery that is affordable, offers value for money, and meets functional needs.