Planning Issues

Dáil Éireann Debate, Thursday - 22 January 2026

Thursday, 22 January 2026

Questions (162)

Barry Heneghan

Question:

162. Deputy Barry Heneghan asked the Minister for Housing, Local Government and Heritage the average timeframe for An Coimisiún Pleanála to determine planning applications remitted by the High Court; the number of such cases currently awaiting decision; the proportion refused to date; the measures being taken to reduce delays and improve certainty in these cases; and if he will make a statement on the matter. [5029/26]

View answer

Written answers

The information requested is not held by my Department

An Coimisiún Pleanála (An Coimisiún) is the national independent statutory body with responsibility for the determination of planning appeals and direct applications for strategic infrastructure and other developments under the Planning and Development Act 2024, as amended, and certain other Acts.

The Planning and Development Act 2024, includes a number of new provisions relating to An Coimisiún, as part of a significant restructure. The Act will introduce statutory time periods for decision making for all consent processes, including, for the first time, for An Coimisiún. This will bring increased certainty to the planning consent processes, for both the public and stakeholders involved in the delivery of key infrastructure such as housing and renewable energy.

For An Coimisiún processes, timelines are being introduced for appeals as well as the various consents applications made directly to An Coimisiún.

It is important to acknowledge that a certain percentage of cases, due to particular circumstances, such as complexity, requests for further information from applicants for permission or further submissions from other participants including third parties, will not meet the 18 week target.

The latest figures received by my Department from An Coimisiún show that 59% of all cases were disposed of within the 18 week target. Performance against this target continues to improve, as 77% of all cases disposed in October 2025 were within the target. 100% of large scale residential appeals have been disposed within the target in 2025. An Coimisiún's processes have continued to improve throughout the year, in preparation for the introduction of statutory timelines for planning decisions as part of the Planning and Development Act 2024.

Arrangements have been put in place by all bodies under the aegis of my Department to facilitate the provision of information directly to members of the Oireachtas. This provides a speedy, efficient and cost effective system to address queries directly to the relevant bodies. The contact email address for An Coimisiún Pleanála in this regard is [Oireachtasqueries@pleanala.ie]