Questions (672)

Pádraig Mac Lochlainn

Question:

672. Deputy Pádraig Mac Lochlainn asked the Minister for Housing, Local Government and Heritage when he will request an organisation (details supplied) to draft a follow up report on construction costs for the defective concrete blocks grant scheme, considering that the last one was almost two years ago. [6420/26]

View answer

Written answers

My Department keeps costs relating to the DCB Scheme under continuous review.

Following updated cost reports from the Society of Chartered Surveyors Ireland (SCSI) and advice from the Expert Group established to consider the matter, a further increase from the original grant rates set down in the Remediation of Dwellings Damaged by the Use of Defective Concrete Blocks Act 2022 (the Act), was provided for on 23 October 2024. The Scheme Cap has risen by 10% to €462,000. An increase in the scheme grant rates of between 7.4% and 8.7% that are set out in the 2023 Regulations was also approved on 7 November 2024.

The Remediation of Dwellings Damaged by the Use of Defective Concrete Blocks (Amendment) Bill 2025 was initiated in Dáil Eireann on 2 December 2025, passed both Houses of the Oireachtas and was subsequently signed into law by the President, thereby becoming an Act, on the 23 December 2025.

The 2025 amendments make provision for the 2024 increases in the Scheme cap and rates to apply to a wider group of relevant owners, along with a number of technical amendments to ensure equity and efficient administration of the Scheme. The related Regulations will be adopted as soon as possible and provide for all matters within the Act which require to be prescribed and will provide the finer detail around how the amendments will operate in the scheme. A date for commencement of the new provisions of the amended Act will also be set as soon as possible.

Costs relating to the scheme are closely monitored and any future changes required to the scheme cap and rates will be dealt with accordingly.