Skip to main content
Normal View

Capital Expenditure Programme

Dáil Éireann Debate, Tuesday - 10 February 2026

Tuesday, 10 February 2026

Questions (319)

Aidan Farrelly

Question:

319. Deputy Aidan Farrelly asked the Minister for Defence the capital works projects currently ongoing at Casement Aerodrome; and when each of those capital works projects will be completed, in tabular form. [10311/26]

View answer

Written answers

The current capital works projects that are ongoing at Casement Aerodrome are listed below:

• St Bricins Re Location – Military Medical Facility; under construction with a 2026 completion

In addition, to date a Masterplan for the airside at Casement Aerodrome has been completed which will provide a programme of projects going forward to feed into the existing Infrastructure Development Plan. A tender competition for a Masterplan for the Landside at Casement will also be completed in the coming weeks which will further add to the future project pipeline.

Share