459. Deputy Conor D. McGuinness asked the Minister for Public Expenditure, Infrastructure, Public Service Reform and Digitalisation to provide a list of all capital works upgrades carried out at Tramore Garda station by the OPW since 2023, in tabular form. [9844/26]

View answer

Written answers

The Office of Public Works (OPW) can confirm that the following works were carried out at Tramore Garda Station since 2023.

Year

Nature of Works

Final Account Cost

2023

Provision of an External Locker Room.

€ 485,077.51

2024

Nil

Nil

2025

Window Replacement

Final accounts have yet to be completed.

2026

Nil

Nil