John Paul O'Shea
Question:519. Deputy John Paul O'Shea asked the Minister for Education and Youth for an update on the capital project for a school (details supplied); and if she will make a statement on the matter. [9136/26]
View answerDáil Éireann Debate, Tuesday - 10 February 2026
519. Deputy John Paul O'Shea asked the Minister for Education and Youth for an update on the capital project for a school (details supplied); and if she will make a statement on the matter. [9136/26]
View answerThe school to which the Deputy referred was approved for funding under the Additional Accommodation Scheme for two projects to provide;
Conversion of existing space to provide a Principal’s Office, Secretary’s Office, and Entrance Lobby. This project was approved to progress on site in 2024 and has since been completed.
Repurposing of space to create three Special Education Tuition (SET) Rooms. This project was approved to progress in 2025 and has now also been fully completed.
All works associated with both projects have been delivered in full, and all related payments have been finalised. There are no further expenditure or actions outstanding.