Skip to main content
Normal View

Natural Gas Grid

Dáil Éireann Debate, Wednesday - 15 April 2026

Wednesday, 15 April 2026

Questions (161)

Ciarán Ahern

Question:

161. Deputy Ciarán Ahern asked the Minister for Climate, Energy and the Environment the volume of biomethane generated in Ireland in each year since 2020; the proportion that was added to the national gas network in each year; the target for biomethane generation in 2026 and 2027 respectively; and if he will make a statement on the matter. [27410/26]

View answer

Written answers

Delivery of the Government's ambition for indigenous biomethane by 2030 and its use within our energy system will have multiple cross-sectoral benefits for Ireland’s economy, energy security and emissions profile. As such, development of the sector will require a coherent and collaborative approach to policy implementation across all sectors including energy, agriculture and enterprise

Biomethane production is still at an early stage of development in Ireland, with two operational biomethane facilities injecting biomethane into the gas grid.

Effectively all biomethane produced in the state has been injected into the national gas network.

Year

Volume

2020

1,013,530 kWh

2021

4,972,394 kWh

2022

40,732,963 kWh

2023

60,120,211 kWh

2024

39,269,434 kWh

2025

10,935,835 kWh

2026

581,389 kWh

There are no individual biomethane generation targets set for 2026 and 2027. Government remains committed to supporting the development of a domestic biomethane industry of scale, and the Biomethane Implementation Group, chaired by my Department, continues to oversee implementation of the National Biomethane Strategy and monitor target delivery. My Department is also working on putting capital grants in place from 2026 to support the development of anaerobic digestion plants in Ireland.

Share