486. Deputy Darren O'Rourke asked the Minister for Education and Youth when construction works at a school (details supplied) will be completed. [27998/26]

View answer

Written answers

The large scale capital project for the school referred to by the Deputy is currently at Stage 4 – Construction.

The project brief is for the construction of a new 1000 pupil Post Primary School building. The development will include the demolition of 6 existing buildings on the site; 5 of which are currently in use by the school, all will be demolished on a phased basis to accommodate the development.

The authorisation to issue the Letter of Acceptance (LOA) was communicated to the Design Team on the 7th of January 2025 commencing the school building project.

The contract duration is an estimated 26 months with a projected completion date in Quarter 2 of 2027.