Dáil Éireann Debate, Tuesday - 28 April 2026

Tuesday, 28 April 2026

Questions (318)

Peter 'Chap' Cleere

Question:

318. Deputy Peter 'Chap' Cleere asked the Minister for Defence the nature of refurbishment works that are scheduled to be carried out at Stephen's Barracks, Kilkenny during 2026, in tabular form.; and if she will make a statement on the matter. [30015/26]

View answer

Written answers

The capital expenditure for building works in military installations and barracks across the country for the last five years was some €170 million.

This year the capital allocation stands at €69.5 million for capital investment with a further €13.5 million allocation for ongoing maintenance and running costs.

Year

Projects

Total Funding (Capital and Design team costs)

2026

New Barrack Accountant Facility (Completed)

€0.63

2026

New Military Equipment Store, Locker Block & Ablution Facility (Design Team Appointed)

N/A - At design stage

2026

Blocks A-F Refurbishment (Design Team Appointed)

N/A - At design stage

In addition, my Department also allocates funding each year to the Defence Forces for the maintenance, repair and upkeep of its building stock. This year a devolved budget of €13.5 million was assigned by my Department to the Defence Forces for these tasks. The individual prioritisation of specific projects to be carried out is solely a matter for the Defence Forces in keeping with the delegated nature of this budget.