Dáil Éireann Debate, Thursday - 30 April 2026

Thursday, 30 April 2026

Questions (293)

Colm Burke

Question:

293. Deputy Colm Burke asked the Minister for Education and Youth the current status of an additional accommodation project application by a school (details supplied); when they can proceed to the next phase; and if she will make a statement on the matter. [31570/26]

View answer

Written answers

The school to which the Deputy refers was approved to enter my departments pipeline to provide for a two-classroom special educational needs (SEN) base. The responsibility for this project has been devolved to the school authority.

A revised Stage 1/2a developed design report was received by my department and is currently being reviewed from both a technical and cost perspective in accordance with the requirements of the Public Infrastructure guidelines. All projects, including this one, will undergo the necessary due diligence outlined in the public Infrastructure Guidelines. Managing timing, scope, and cost is crucial to staying within budgetary limits for the overall program.

As the Deputy will be aware, I have recently published the €7.55 billion NDP Sectoral Investment Plan for the Education and Youth Sectors for the period 2026 to 2030. As part of planning ahead for the next tranche of projects to progress to tender, the department led prioritisation process will continue over the course of 2026 and 2027 to assess and evaluate the progression of individual projects through the design pipeline having regard to the continual need to maximise existing capacity and determine the prioritised needs going forward. This process will involve engagement with key stakeholders and individual schools and will ultimately inform the next tranches of programme rollout to tender. The department-led Energy and Condition Survey of the school estate, which will be finalised later in 2026, will provide an additional evidence base for assessing priorities.

Based on this ongoing prioritisation process some projects may be added to the list over the course of 2026 and 2027 having regard to their prioritisation and urgency of need and taking account also of the ongoing ability to progress them to tender and construction within the parameters of overall funding. Where appropriate, my department will also assess opportunities to undertake advance enabling works for the most urgent and complex projects to facilitate a smooth progression to construction in 2028 and beyond.

The accommodation needs at this school will be considered as part of the ongoing overall department-led prioritisation process, in consultation with the school’s patron and school authorities.