179. Deputy Emer Currie asked the Minister for Defence if she will provide a list of all capital projects, including Defence Forces infrastructure projects, delivered under the remit of her Departments which have been completed on time and within budget in Dublin West in each of the past five years, in tabular form; and if she will make a statement on the matter. [33673/26]

View answer

Barry Ward

Question:

181. Deputy Barry Ward asked the Minister for Defence if she will provide a list of all capital projects, including Defence Forces infrastructure projects, delivered under the remit of her Department which have been completed on time and within budget in Dublin in each of the past five years, in tabular form; and if she will make a statement on the matter. [33820/26]

View answer

Written answers

I propose to take Questions Nos. 179 and 181 together.

The capital expenditure for building works in military installations and barracks across the country for the last five years was some €170 million. This year the capital allocation stands at €69.5 million for capital investment with a further €13.5 million allocation for ongoing maintenance and running costs.

The information sought by the Deputy is as follows:

Year of Completion

Project

Project Cost Inc VAT

2025

Casement Aerodrome: Modular Accommodation

€2m

2024

Casement Aerodrome: Main Technical Stores Refurbishment

€0.9m

2024

McKee Barracks: New MTF Former Chief of Staff House Upgrade

€1.45m

2024

McKee Barracks: Printing Press relocation

€2.32m

2024

Casement Aerodrome: Hangar 3 upgrade and new door

€1.36m

2024

McKee Barracks: Upgrade of Block F

€17.57m

2024

McKee Barracks: New Locker Block

€1.83m

2023

McKee Barracks: Refurbishment of East Wall Building

€0.75m

2023

Casement Aerodrome: Hangar 3 Roof-light replacement

€0.3m

2022

Casement Aerodrome: Runway Led Lights

€0.47m

2022

McKee Barracks: Refurb of Block H

€6.58m

2022

McKee Barracks: Guard Room Roof Upgrade

€1.12m

2022

Casement Aerodrome: Watermains upgrade

€1.16m

2021

Casement Aerodrome: Replace of standby generators at Casement Aerodrome

€0.22m

In addition, my Department also allocates funding each year to the Defence Forces for the maintenance, repair and upkeep of its building stock. This year a devolved budget of €13.5 million was assigned by my Department to the Defence Forces for these tasks. The individual prioritisation of specific projects to be carried out is solely a matter for the Defence Forces in keeping with the delegated nature of this budget.