302. Deputy Roderic O'Gorman asked the Minister for Defence the nature of refurbishment works that were carried out at Defence Forces Equitation School in the years of 2024, 2025 and to date in 2026, in tabular form; and to list the works that are scheduled to commence at the Equitation School during the second half of this year. [34584/26]

View answer

Written answers

I can advise the Deputy that the following works are being carried out at the Equitation School and Stables at McKee Barracks which are due to be completed in the coming weeks:

Year of Commencement

Project

Cost incl. VAT

2025

Refurbishment of Stable Blocks 1, 2 and 3

€1,228,082.84

The Deputy may also wish to note that my Department also allocates funding each year to the Defence Forces for the maintenance, repair and upkeep of its building stock. This year a devolved budget of €13.5 million was assigned by my Department to the Defence Forces for these tasks. The individual prioritisation of specific projects to be carried out is solely a matter for the Defence Forces in keeping with the delegated nature of this budget.