Thomas Gould
Question:731. Deputy Thomas Gould asked the Minister for Housing, Local Government and Heritage for an update on the North-West Quarter regeneration, in Cork, by phase status, in tabular form. [40106/26]
View answerDáil Éireann Debate, Tuesday - 26 May 2026
731. Deputy Thomas Gould asked the Minister for Housing, Local Government and Heritage for an update on the North-West Quarter regeneration, in Cork, by phase status, in tabular form. [40106/26]
View answerPlease see below timeline for delivery of the Cork North West Quarter Regeneration (CNWQR) projects, by phase. Please note that Table 1 below includes projects that are fully approved; Table 2 includes projects that are going through the approval process.
Responsibility for the progression of individual projects and the associated delivery timelines lie with Cork City Council.
Table 1.
|
Project Name |
No of Units |
Project Status |
Construction Status |
Projected Delivery Date/Completion Date |
|
CNWQR Croppy Boy Phase 1 |
24 |
Contract Awarded |
Onsite |
Q3 2026 |
|
CNWQR Knocknaheeny Phase 1B |
29 |
Complete |
Completed |
Q3 2017 |
|
CNWQR Knocknaheeny Phase 1C |
41 |
Complete |
Completed |
Q4 2025 |
|
CNWQR Knocknaheeny Phase 2A |
47 |
Complete |
Completed |
Q4 2019 |
|
CNWQR Knocknaheeny Phase 2B |
38 |
Contract awarded |
Onsite |
Q2 2026 |
|
Regen CNWQR Knocknaheeny Phase 3B |
62 |
Contract Awarded |
Onsite |
Q2 2027 |
Table 2.
|
Project Name |
No of Units |
Project Status |
Construction Status |
Projected Delivery Date/Completion Date |
|
CNWQR Croppy Boy Phase 4C West |
20 |
Pre Planning |
Not Started |
Q2 2028 |
|
CNWQR Knocknaheeny Phase 4 F |
23 |
Pre Planning |
Not Started |
Q1 2028 |
|
CNWQR Knocknaheeny Phase 3C |
24 |
Pre Planning |
Not Started |
Q4 2028 |
|
CNWQR Knocknaheeny Phase 3A |
15 |
Pre Planning |
Not Started |
Q4 2028 |
|
CNWQR Knocknaheeny Phase 1D East |
14 |
Pre Tender |
Not Started |
Q1 2028 |
|
Regen CNWQR Knocknaheeny Phase 4A |
43 |
Pre Tender |
Not Started |
Q4 2028 |