The Office of Public Works is a key service provider to Government, managing the State's estate portfolio, maintaining and presenting Ireland's built heritage, and leading the State's flood risk management function. Under the current National Development Plan, the OPW has secured a record allocation of €1.845 billion, encompassing flood risk management, State property management, and the conservation of heritage assets in support of regional tourism. The OPW's capital programme is one of the most geographically distributed and functionally diverse in the public service, with works delivered in every county.
Capital investment in any given area in a particular year reflects a range of demand-led factors rather than a fixed geographical allocation. Under Estate Management, the OPW is responsible for the maintenance, refurbishment, and development of government properties including offices, Garda stations, and other public service buildings. Across the estate, ongoing maintenance is essential to ensure that public assets remain safe, functional, and efficient. Regular maintenance activities frequently identify areas where more substantial interventions are required, leading to planned preventative capital works. By integrating insights from ongoing maintenance into capital planning, the OPW ensures that resources are used effectively and future risks are minimised.
Accessibility requirements also drive capital investment in the OPW's property portfolio. The OPW in recent years completed universal access works at Dún Laoghaire Garda Station. The attached table sets out many of the significant OPW capital works progressing in 2026 in the Dun Laoghaire-Rathdown area.
Flood Risk Management represents a further significant pillar of OPW activity in Dún Laoghaire-Rathdown. The OPW is working in partnership with Dún Laoghaire-Rathdown County Council to advance major flood relief schemes in the area, including the Loughlinstown Flood Relief Scheme. While Loughlinstown is a single scheme, it encompasses two river catchments Deansgrange and Carrickmines/Shanganagh. The Carrickmines/Shanganagh element is currently in the planning process with An Coimisiún Pleanála. Subject to planning consent, it is expected to commence construction in Q1 2028 and the Deansgrange element expected to commence construction in Q1 2027. The estimated project budget for the Loughlinstown FRS is €26.9m. Further information on flood risk management activity in County Dublin is available at floodinfo.ie/county-summary.
|
Location
|
OPW Capital Works
|
Status
|
|
|
Windows Refurbishment
|
Contract awarded
|
|
Cabinteely Garda Station
|
Roofworks
|
Contract awarded
|
|
|
Electrical systems upgrade works
|
Design stage
|
|
Dun Laoghaire Garda Station
|
Roofworks
|
Design stage
|
|
Dun Laoghaire Probation and Welfare
|
Consolidation of Office space
|
Design stage
|
|
Shankill Garda Station
|
Carpark resurfacing works
|
Design stage
|
|
Clonskeagh, Belfield , Offices for the National Shared Services Office
|
Facilities upgrade works to 2nd and 4th floor
|
Tender issued
|
|
Dun Laoghaire Courthouse
|
Roof works
|
Contract awarded
|
|
Dundrum Garda Station
|
Electrical systems upgrade works
|
Design stage
|