I propose to take Questions Nos. 317 and 318 together.
My department has a strong track record of delivering the school building programme with over €6.9 billion invested since 2020. This has delivered approximately 1,400 completed school building projects and over 4,000 smaller-scale improvement projects.
Last January, I published the €7.55 billion NDP Sectoral Investment Plan for the education and youth sectors for the period 2026 to 2030. This NDP Sectoral Plan involves a very strong emphasis on maximising existing capacity and prioritisation of school building projects to meet the most urgent needs.
Of the total €7.55 billion investment, it is envisaged that approximately €5 billion will be used for project rollout to support the delivery and modernisation of school buildings. This project rollout will continue on a prioritised basis to meet the most urgent needs in terms of provision of additional capacity and modernisation of existing facilities. In this regard, I have also published a list of the 105 school building projects in a first tranche to proceed to construction or tender over 2026 and 2027. These projects were prioritised with a strong focus on maximising existing capacity and prioritising project rollout to meet the most urgent needs particularly to support special education needs provision.
The first tranche of?projects being progressed to tender and/or construction over the course of 2026 and 2027 was published in January. This involves 80 large scale and extension projects, as well as 25 modular projects. The number of priority modular projects has since increased to over 60, reflecting in particular the urgency of providing accommodation for special education classes where no existing capacity is available.
The 80 prioritised large scale and extension projects included 45 projects already at Stage 3 (tender stage) last January.
The remaining 35 projects were already at Stage 2b (pre-tender stage) with planning permission. This group of projects were prioritised to meet the most urgent requirements from a special needs perspective or to provide additional capacity to cater for demographics or to address very significant condition issues at the schools. The majority of new school buildings included in this category were either for special schools or schools that are operating fully from interim accommodation and have an urgent need for permanent accommodation.
Schools that did not already have planning permission were not considered for inclusion in the initial tranche as they were not at an appropriate stage of readiness.
Prioritised projects continue to be progressed through earlier stages of the design pipeline, with a focus on special schools; schools fully in interim accommodation, with an urgent requirement for permanent accommodation; projects delivering significant special education capacity; additional accommodation required to cater for demographic growth in an area; and projects dealing with the most significant condition issues.
As part of a department-led prioritisation process that will continue over 2026 and 2027, consultation with school patrons commenced this month. The publication of a further tranche of priority projects to progress to tender is targeted for 2027. This will be informed by department analysis, engagement with patrons and schools, funding parameters and, where relevant, the department’s energy and condition inventory of the school estate which is scheduled to be completed by the end of the year. Projects must also be at an appropriate stage of readiness to be considered for approval in the next tranche; this means that projects not already at Stage 2a currently are unlikely to be eligible for consideration
Some additional priority modular projects have been added to the list for delivery in 2026 and 2027 and further projects may be added having regard to urgency of need and affordability within annual funding parameters.
Where appropriate, my department will also assess opportunities to undertake advance enabling works for the most urgent and complex large-scale projects to facilitate a smooth progression to construction in 2028 and beyond.
Any interim accommodation requirements identified by schools will continue to be assessed and considered by the Department on a case-by-case basis to determine the prioritised needs and approach for addressing same.
Separately, many schools this year will continue to benefit from investments under the climate action summer works scheme, other climate action initiatives, repurposing for special education classes, and the emergency works scheme.
It is important to note that the 105 projects on the initial NDP priority list represent a subset of the overall school building programme. In total, there are 260-300 projects under construction at any one time. Over the course of 2026, some 1,000 school projects of varying scales will be under construction. In addition to large scale, extension and modular projects, this includes climate action projects, summer works and repurposing of rooms for special education classes.