Wind Energy Generation

Dáil Éireann Debate, Thursday - 16 July 2026

Thursday, 16 July 2026

Questions (233)

Pa Daly

Question:

233. Deputy Pa Daly asked the Minister for Climate, Energy and the Environment the proportion of the 2030 target for offshore wind that has been achieved (energised) to date in 2026; and if he will make a statement on the matter. [54739/26]

View answer

Written answers

Five Phase 1 offshore wind projects are presently in development off our East coast, with planned capacity of 3.8 gigawatts (GW). All five have submitted planning applications and first determinations from An Coimisiún Pleanála are anticipated before the end of 2026, with the others to follow in 2027. Subject to planning approval, and the progression of the projects by the developers, I anticipate that some of these projects will be in construction by 2030 and operational in the early 2030s.

The 900 MW Tonn Nua project off the coast of Waterford is progressing well since approval in 2025. Tonn Nua was the first of four sites to be brought to auction from the South Coast DMAP. My Department is making preparations to bring the remaining three South Coast DMAP sites to auction over the next few years.

Separately, my Department is advancing the National DMAP process, which will designate sufficient additional sites around our coast to facilitate our longer term target of 20 GW.

The international market situation for offshore wind has changed much since Ireland's first offshore wind auction in 2023. Prices in the supply chain have increased, many offshore wind developers have rationalised their operations and now have a more risk averse investment outlook, and many jurisdictions have seen failed auctions for various reasons.

This changed market environment presents challenges for all nations in progressing their offshore wind ambitions. I am maintaining a regular dialogue with our offshore wind industry, and in particular our Phase 1 projects, as we navigate these challenges.

While this more challenging international market environment has the potential to impact on the timing of achievement of particular milestones in our offshore wind ambitions, Government remains committed to achieving those ambitions.