Question:592. Deputy Thomas Gould asked the Minister for Housing, Local Government and Heritage the timeline for delivery of the Northwest Quarter Regeneration, by phases, in Cork. [72144/25]
View answerDáil Éireann Debate, Tuesday - 16 December 2025
592. Deputy Thomas Gould asked the Minister for Housing, Local Government and Heritage the timeline for delivery of the Northwest Quarter Regeneration, by phases, in Cork. [72144/25]
View answerPlease see below timeline for delivery of the Cork North West Quarter Regeneration (CNWQR) projects, by phase. Please note that the table below only includes projects that are fully approved; it does not include projects that are still going through the approval process.
Responsibility for the progression of individual proje
|
Project Name |
Phase |
No of Units |
Project Funding Status |
Construction Status |
Projected Delivery Date/Completion Date |
|
CNWQR Croppy Boy Phase 1 |
1/1 |
24 |
Stage 4 Approved |
Onsite |
Q4 2025 |
|
CNWQR Knocknaheeny Phase 1B |
1/1 |
29 |
Complete |
Completed |
Q3 2017 |
|
CNWQR Knocknaheeny Phase 1C |
1/1 |
41 |
Stage 4 Approved |
Onsite |
Q4 2025 |
|
CNWQR Knocknaheeny Phase 2A |
1/1 |
47 |
Complete |
Completed |
Q4 2019 |
|
CNWQR Knocknaheeny Phase 2B |
1/1 |
38 |
Stage 4 Approved |
Onsite |
Q2 2026 |
|
Regen CNWQR Knocknaheeny Phase 3B |
1/1 |
62 |
Stage 4 Approved |
Not Started |
Q2 2027 |