Regeneration Projects

Dáil Éireann Debate, Tuesday - 16 December 2025

Tuesday, 16 December 2025

Ceisteanna (592)

Thomas Gould

Ceist:

592. Deputy Thomas Gould asked the Minister for Housing, Local Government and Heritage the timeline for delivery of the Northwest Quarter Regeneration, by phases, in Cork. [72144/25]

Amharc ar fhreagra

Freagraí scríofa

Please see below timeline for delivery of the Cork North West Quarter Regeneration (CNWQR) projects, by phase. Please note that the table below only includes projects that are fully approved; it does not include projects that are still going through the approval process.

Responsibility for the progression of individual proje

Project Name

Phase

No of Units

Project Funding Status

Construction Status

Projected Delivery Date/Completion Date

CNWQR Croppy Boy Phase 1

1/1

24

Stage 4 Approved

Onsite

Q4 2025

CNWQR Knocknaheeny Phase 1B

1/1

29

Complete

Completed

Q3 2017

CNWQR Knocknaheeny Phase 1C

1/1

41

Stage 4 Approved

Onsite

Q4 2025

CNWQR Knocknaheeny Phase 2A

1/1

47

Complete

Completed

Q4 2019

CNWQR Knocknaheeny Phase 2B

1/1

38

Stage 4 Approved

Onsite

Q2 2026

Regen CNWQR Knocknaheeny Phase 3B

1/1

62

Stage 4 Approved

Not Started

Q2 2027