Conor Sheehan
Question:336. Deputy Conor Sheehan asked the Minister for Transport for an update on the construction timeline and funding of a train station (details supplied); and if he will make a statement on the matter. [17124/26]
View answerDáil Éireann Debate, Tuesday - 3 March 2026
336. Deputy Conor Sheehan asked the Minister for Transport for an update on the construction timeline and funding of a train station (details supplied); and if he will make a statement on the matter. [17124/26]
View answerAs Minister for Transport, I have responsibility for policy and overall funding in relation to public transport. The National Transport Authority (NTA) has responsibility for the planning and development of public transport infrastructure including, together with Iarnród Éireann, the works at Moyross train station.
Planning permission for Moyross was granted by Limerick City and County Council in October 2025 and construction is expected to commence this year.
Noting the NTA's responsibility in this matter and the specific queries raised by the Deputy, I have referred the Deputy's questions to the NTA for a more detailed reply. Please contact my private office if you do not receive a reply within 10 days.