Road Projects Status

Dáil Éireann Debate, Wednesday - 24 September 2014

Wednesday, 24 September 2014

Ceisteanna (211)

Derek Nolan

Ceist:

211. Deputy Derek Nolan asked the Minister for Transport, Tourism and Sport the start date for the new Gort to Tuam motorway in County Galway; and if he will make a statement on the matter. [36001/14]

Amharc ar fhreagra

Freagraí scríofa

As Minister for Transport, Tourism and Sport, I have responsibility for overall policy and funding in relation to the national roads programme.  The planning, design and implementation of individual road projects  (including the Gort to Tuam PPP) is a matter for the National Roads Authority (NRA) under the Roads Acts 1993 to 2007 in conjunction with the local authorities concerned.  

Since the contract for the Gort to Tuam scheme was signed work has been underway on the project.  As regards the detail of  the construction schedule, I have referred the Deputy's question to the NRA for direct reply. Please contact my private office if you have not received a response within 10 working days.

Roinn