Dáil Éireann Debate, Tuesday - 30 January 2024

Tuesday, 30 January 2024

Ceisteanna (322, 323, 324, 325)

Eoin Ó Broin

Ceist:

322. Deputy Eoin Ó Broin asked the Minister for Housing, Local Government and Heritage the average cost of a new build social home delivered via turnkey in 2023, broken down by local authority, in tabular form. [3795/24]

Amharc ar fhreagra

Eoin Ó Broin

Ceist:

323. Deputy Eoin Ó Broin asked the Minister for Housing, Local Government and Heritage the average cost of a new build social home delivered via SHIP construction in 2023, broken down by local authority, in tabular form. [3796/24]

Amharc ar fhreagra

Eoin Ó Broin

Ceist:

324. Deputy Eoin Ó Broin asked the Minister for Housing, Local Government and Heritage to provide in tabular form the average cost of a new build social home delivered via CALF construction in 2023 broken down by local authority. [3798/24]

Amharc ar fhreagra

Eoin Ó Broin

Ceist:

325. Deputy Eoin Ó Broin asked the Minister for Housing, Local Government and Heritage to provide in tabular form the average cost of a new build social home delivered via Part V in 2023 broken down by local authority. [3799/24]

Amharc ar fhreagra

Freagraí scríofa

I propose to take Questions Nos. 322, 323, 324 and 325 together.

The relevant details are being compiled and will be provided to the Deputy in accordance with Standing Orders.

Question No. 323 answered with Question No. 322.
Question No. 324 answered with Question No. 322.
Question No. 325 answered with Question No. 322.
The following deferred reply was received under Standing Order 51.
My Department assesses, approves and records local authority social housing delivery on a project basis. As SHIP-funded construction projects by local authorities must, like all publicly-funded construction programmes, comply with the Infrastructure Guidelines (Public Spending Code) and Capital Works Management Framework, my Department periodically issues Basic Unit Costs (formerly UCCs) for each local authority area, for use as a key benchmark for the development and costing of scheme designs at capital appraisal stage. While not a record of actual delivery costs, BUCs are based on an analysis of returned data from tendered social housing schemes over an extended period and updated based on published tender index information as required. To monitor tender cost trends and to inform BUC levels, my Department analyses the tender data for the construction cost element of new build schemes approved under the four stage approval processes for each unit type, where sufficient information is available to allow such costs to be extrapolated and where the information available is appropriate for comparison purposes. Outlined in the table below are average construction costs per unit (incl. VAT), for each local authority, recorded as part of the aforementioned analysis for projects tendered in the years 2022 & 2023.
The tables also set out the range of average unit costs (across different projects) for each local authority. The range of costs recorded vary, depending on design, mix of unit types (e.g. bedroom numbers, apartment/house); and on the level of abnormal requirements for each scheme, for instance existing site conditions, demolitions, service diversions, site access requirements. Average abnormal costs are also separately identified in the table.

SHIP Construction

Construction Costs (incl abnormals)

Construction Costs (incl abnormals)

Abnormal Costs

LA

Average Cost Per Unit

Range of Costs Per Unit

Average Cost Per Unit

Carlow

215,423

215k - 215k

10,289

Cavan

282,599

278k - 294k

38,514

Clare

279,726

268k - 289k

56,596

Cork City

316,095

244k - 364k

48,171

Cork County

271,427

165k - 321k

45,705

DLR

347,005

252k - 376k

29,085

Donegal

230,574

191k - 257k

21,833

Dublin City

386,391

381k - 390k

46,177

Fingal

248,256

242k - 287k

22,595

Galway City

243,328

226k - 421k

23,963

Galway County

234,634

224k - 287k

23,048

Kerry

264,727

231k - 363k

29,200

Kildare

364,123

317k - 371k

57,853

Kilkenny

340,559

341k - 341k

47,678

Laois

327,552

328k - 328k

45,414

Leitrim

N/A

N/A

N/A

Limerick City

248,213

196k - 261k

31,215

Longford

236,571

237k - 237k

23,758

Louth

317,397

296k - 359k

39,455

Mayo

270,256

249k - 319k

39,872

Meath

299,198

222k - 344k

21,928

Monaghan

248,656

249k - 249k

33,894

Offaly

263,567

264k - 264k

24,589

Roscommon

194,389

180k - 213k

17,689

Sligo

242,150

206k - 301k

24,728

South Dublin

356,789

327k - 365k

35,884

Tipperary

219,300

219k - 219k

25,053

Waterford City

273,532

221k - 302k

52,658

Westmeath

263,361

250k - 434k

21,407

Wexford

334,161

262k - 373k

38,677

Wicklow

338,425

170k - 406k

49,244

The costs to the construction element only of the all-in delivery cost. Other items that make up the all-in total include:
• Design/technical fees: Design fees vary from project to project, depending on the location, size and complexity of a scheme (and depending on whether design services are provided by a local authority in-house or via external appointment). As a guideline/indicator, design fee are generally expected to range between 7.5% to 12.5% of construction costs.
• Land cost: Land costs will vary significantly from project to project, depending on location and ownership status (i.e. land costs could vary from existing local authority land at no cost to land purchased at market value).
• Utilities: Connection fees for Irish Water, ESB, gas, etc. As a guideline/indicator, utility connection costs are generally in the order of €7k per unit.
• Other Costs: Other items that make up the all-in delivery cost can include site investigations/surveys, archaeological requirements, Percent for Art contributions - and will vary from scheme to scheme.
In advancing social housing projects, a range of factors can impact on the costs for individual projects. Project-specific issues will always arise and can impact on how a project can be advanced and the costs for same. These factors are covered in the regular engagement that happens between my Department and local authorities which is focussed on facilitating the earliest possible delivery of new social homes.
My Department publishes comprehensive programme level statistics on a quarterly basis on social housing delivery activity by local authorities and Approved Housing Bodies (AHBs) in each local authority. This data is available to the end of Quarter 3 2023 and is published on the statistics page of my Department’s website at the following link: www.gov.ie/en/publication/6d316-local-authority-housing-scheme-statistics/?referrer=http://www.housing.gov.ie/housing/social-housing/local-authority-housing-scheme-statistics My Department also publishes the Social Housing Construction Status Report (CSR). The CSR provides details of social housing developments and their location that have been completed, are under construction or are progressing through the various stages of the design and tender processes. The most recent publication was for Quarter 3 2023. All Construction Status Reports are available at the following link: www.gov.ie/en/collection/cb885-social-housing-construction-projects-status-reports/ A version of the CSR file can also be downloaded for analysis of completions, locations, approvals stage etc. at this link:
https://data.gov.ie/dataset/social-housing-construction-status-report-q3-2023
Data for Q4 2023 is currently being collated.
The table in the pdf attached sets out the average cost per social housing homes delivered across SHIP Turnkey, CAS and CALF build programmes for the first 9 months of 2023.
Note 1: The information provided in the table is based on the financial information available to the Department. Delivery does not necessarily occur in the year of approval or spend.
Note 2: Agreement on Part V arrangements are a matter for the local authorities. In some cases the Part V average is affected by delivery of homes that were subject to agreements prior to the current Part V arrangements. Complete details of PART V arrangements are available from the local authorities. It should be noted that some Part Vs, while recorded as delivered in 2021, costs have not been claimed or recouped as yet and so are excluded from the average costs below. The CAS Part V average is based on the cost of providing one unit in a shared accommodation dwelling.
Roinn