Harbours and Piers

Dáil Éireann Debate, Wednesday - 19 June 2024

Wednesday, 19 June 2024

Ceisteanna (159)

Catherine Connolly

Ceist:

159. Deputy Catherine Connolly asked the Minister for Rural and Community Development further to Parliamentary Question No. 15 of 9 May 2024, for a status update on the development of Inis Oírr pier; and if she will make a statement on the matter. [26511/24]

Amharc ar fhreagra

Freagraí scríofa

As the Deputy is aware, Galway County Council is the responsible authority for the maintenance and development of pier infrastructure on the Aran Islands.

In July 2023, I gave approval to Galway County Council to issue a request for tender for the development of the Inis Oírr pier. Galway County Council is the contracting authority and is therefore responsible for all aspects of the procurement process.

I understand that a two-stage tender process is currently underway and that Galway County Council have published the Stage 2 tender documents.

I am advised that Galway County Council has extended the closing date for receipt of Stage 2 tender responses by 4 weeks, to mid August.

The assessment and evaluation of all valid tender responses will be carried out by Galway County Council and should take approximately 2 months. Subject to the successful completion of this procurement process, it is expected that a contractor will be appointed later this year.

I can assure the Deputy that I am determined that we maintain the momentum to get this project underway and completed.