39. Deputy Cian O'Callaghan asked the Minister for Education if she will outline, in relation to the Donaghmede/Howth/D13/Baldoyle/Stapolin school planning area, how her Department assesses the demand for secondary school places where significant new developments are being constructed; if this assessment takes place in the planning of new developments or after the developments are built; and if she will make a statement on the matter. [26343/24]

Amharc ar fhreagra

Freagraí scríofa

The provision of school places to meet the needs of children and young people at primary and post primary level, including children and young people with special educational needs is an absolute priority for the Department.

In order to plan for school provision and analyse the relevant demographic data, my Department divides the country into 314 school planning areas and uses a Geographical Information System, using data from a range of sources, including CSO Census data, Child Benefit and school enrolment data, to identify where the pressure for school places across the country will arise and where additional school accommodation is needed at primary and post-primary level.

Major new residential developments have the potential to alter the demand for school places at a local level. In that regard, as part of the demographic demand analysis, my Department monitors planning and construction activity in the residential sector. This involves the analysis of data sources from Local Authorities and the CSO along with the engagement with local authorities and the construction sector. In this way, up-to-date information on significant new residential developments is obtained and factored into the demographic analysis exercise. This is necessary to ensure that schools infrastructure planning is keeping pace with demographic changes, at a local level, where there is a constantly evolving picture with planned new residential development.

It is important to note that where enrolment pressures arise, it may not always be as a result of lack of accommodation but may be driven by the following factors:

• Duplication of applications – pupils have applied for a place to a number of schools in the area

• School of choice – pupils can’t get a place in their preferred school while there are places in other schools in the town/area

• Some towns/areas have single sex schools and while places are available in the school they are not available to all pupils

• External draw – pupils coming from outside the local area.

Where demographic data indicates that additional provision is required, the delivery of such additional provision is dependent on the particular circumstances of each case and may, be provided through: utilising existing unused capacity within a school or schools, extending the capacity of a school or schools, provision of a new school or schools.

My Department's main responsibility is to ensure that schools in an area can, between them, cater for all pupils seeking school places in the area. If additional accommodation is required, the aim to try and facilitate this, as much as possible, by way of expansion of existing schools rather than establishing new schools. The expansion of existing schools is consistent with wider Government objectives under Project Ireland 2040 for an increased emphasis on compact growth. In respect of post primary schools, new post primary schools must have a student enrolment capacity of 600-1,000 students and must be co-educational. A lower threshold of 400 students may apply to Gaelcholáistí, having regard to the alternative of establishing an Irish-medium unit (Aonad) in an English-medium school.

New schools are only established in areas of demographic growth as the resources available for school infrastructure have to be prioritised to meet the needs of areas of significant population increase so as to ensure that every child has a school place.

There are currently a number of active projects at in the Donaghmede_Howth_D13 School Planning Areas which will increase local capacity. The Capital Programme details the school projects that are being progressed under Project Ireland 2040. The current status of large-scale projects being delivered under Project Ireland 2040, may be viewed on my Department's website at, www.gov.ie and this information is updated regularly. In addition, a list of large-scale projects completed from 2010 to date may also be viewed on the website.

The pace of delivery of additional residential development in the school planning areas, along with updated enrolment data and demographic data will be kept under review and this will inform the timing of school requirements. The Department will continue to liaise with Local Authorities in respect of their County Development Plan and any associated Local Area Plans with a view to identifying any potential long-term school accommodation requirements across school planning areas.