Léim ar aghaidh chuig an bpríomhábhar
Gnáthamharc

National Children's Hospital

Dáil Éireann Debate, Tuesday - 9 July 2024

Tuesday, 9 July 2024

Ceisteanna (700)

Patrick Costello

Ceist:

700. Deputy Patrick Costello asked the Minister for Health the reason the new National Children’s Hospital is fully lit up at night once construction has ceased for the day; the estimated number of electrical units currently being expended outside the operation of construction; and the cost of same to the State. [29228/24]

Amharc ar fhreagra

Freagraí scríofa

The National Paediatric Hospital Development Board (NPHDB) has statutory responsibility for planning, designing, building, and equipping the new children's hospital. I have therefore referred your question to the NPHDB for direct reply.

Roinn