Sorca Clarke
Ceist:662. Deputy Sorca Clarke asked the Minister for Education the funding provided for capital projects for schools in County Wexford from 2021 to date in 2024, in tabular form. [35492/24]
Amharc ar fhreagraDáil Éireann Debate, Monday - 9 September 2024
662. Deputy Sorca Clarke asked the Minister for Education the funding provided for capital projects for schools in County Wexford from 2021 to date in 2024, in tabular form. [35492/24]
Amharc ar fhreagraSince 2020, the department has invested in the region of €5 billion in our schools throughout the country, involving the completion of over 950 school building projects and with construction currently underway at approximately 350 other projects, which includes 36 new school buildings. These 350 projects currently at construction involve a total State investment of over €1.5bn.
The Department announced earlier in the year that close to 90 projects, including 28 new school buildings, would be authorised to proceed from tender stage to construction over the course of 2024 and early 2025. In total, around €800 million will be invested in these projects under the department’s Large Scale Capital Programme and Additional Accommodation Scheme for essential classroom accommodation.
Between projects currently under construction and projects moving to construction in this latest phase, investments by the Department of Education are adding over 550,000 square metres of new and modernised capacity to our school estate.
This is a record level of investment in school buildings. It will expand the number of school places, significantly increase provision for special education and upgrade and modernise our school infrastructure. The impact of this will be felt in communities right around the country.
The key drivers of capital investment in the school sector include:
• demographic growth, particularly at post primary level
• increased demand for special educational needs provision
• alignment of school place provision with new housing development
• climate action objectives including deep energy retrofit.
Since 2021, over €100 million has been invested in Co. Wexford schools under the school building programme.
Between 2021 to date, 40 school building projects have been completed in Co. Wexford.
Currently there are 17 school building projects under construction in Co. Wexford.
There are also 45 school building projects (Large Scale/ASA/Modular) in Co. Wexford moving through the various stages of design, of which 5 are new school projects.
These projects are being delivered to ambitious timeframes, and the position on individual projects evolves all the time as they advance through various stages. The status of all projects is set out at (www.gov.ie). This is updated on a regular basis to reflect project progress through the various stages of capital appraisal, site acquisition, design, tender and construction.
The table below provides details of yearly investment in the School Building Programme in Co. Wexford from 2021 to date.
|
Capital Expenditure on School Building Projects in Co. Wexford |
|||
|
2021 |
2022 |
2023 |
2024 |
|
€19m |
€29m |
€32m |
€21m |