Dáil Éireann Debate, Monday - 9 September 2024

Monday, 9 September 2024

Ceisteanna (736)

Rose Conway-Walsh

Ceist:

736. Deputy Rose Conway-Walsh asked the Minister for Tourism, Culture, Arts, Gaeltacht, Sport and Media for an update on all-island arts capital investment projects; to provide the total allocation; the expenditure to date; the amount that is contained with expenditure ceilings laid out in the stability programme update and summer economic statement and the amount that will have to come from additional funding; the date the project was started; and the projected date of completion, in tabular form; and if she will make a statement on the matter. [34828/24]

Amharc ar fhreagra

Freagraí scríofa

There are five all-island Arts capital investment projects, that are being funded with a total allocation of €7.4 million from the Government’s Shared Island Fund and are presented in tabular form below.

Project/Grantee

Total allocation €

Expenditure to date €

Amount to from other funding €

Date project started

Projected date of completion

Irish Architectural Archive

100,000

99,794

0

2023

Completed 2023

Irish Film Institute

200,000

200,000

0

2023

Completed 2023

Irish Traditional Music Archive

1m

250,000

0

2023

2026

Tyrone Guthrie Centre

1.5m

0

0

2024

2026

Bellaghy Bawn writers residence

4.6m

0

0

2023

2027