The Renewable Energy Support Scheme (RESS) Community Enabling Framework was launched in 2022. It provides a range of supports, including grant funding of potentially up to €180,000, offered from SEAI to community renewable energy projects, to help them participate in the RESS. To date, two community projects (both under RESS 1 in 2022), including one solar and one wind, have received €40,000 each in grant funding.
My Department is working closely with the SEAI and community groups to assess the barriers to community energy projects, to ensure a long term sustainable future for the community energy sector in Ireland. In that regard, community projects will now transition to the non-competitive Small-Scale Renewable Electricity Support Scheme (SRESS), enabling community projects to maximise their participation in the energy transition.
The first phase of SRESS was launched in July 2023. This sees both SRESS and the Microgeneration Support Scheme (MSS) providing support to communities, larger businesses, farms, and public buildings, with grants that support solar installations for self-consumption. These SEAI non-domestic scheme grants are supporting renewables self-consumers to invest in systems of up to 1MW in size. A total of 2,069 grants applications have been received, including, for the Community and Sports Sector, 117 grant applications amounting to funding of €994,039 and a total installation capacity of over 7.9 MW.
In May I announced the tariffs for the export tariff phase of SRESS, which will support small-scale and community renewable projects. In the largest SRESS category, communities will receive a guaranteed tariff 20% higher than the average community price in the most recent RESS auction for community projects in 2022. The export project tariff phase of SRESS, is due to open for applications by the end of the year, and will be a major step forward in supporting the community energy sector.
A set of technical and financial supports for community projects are currently available to communities through the Community Enabling Framework under the RESS. Similar supports will be available under the SRESS.
In addition, in 2023 and 2024, SEAI also undertook seven county level grid studies to support communities in identifying sites that are most likely to have an economically viable grid connection.
In September, the Commission for Regulation of Utilities published the new Electricity Connection Policy – Generation and System Services policy. The new policy provides greater opportunities for connection to the electricity network for community renewable energy projects through provisions such as the reduction in the first stage grid payment fees; the removal of upper and lower capacity limits; the size of projects not required to pay a capacity bond increasing from 5MW to 6MW; and the removal of caps on the number of projects per processing batch.