Schools Building Projects

Dáil Éireann Debate, Wednesday - 6 November 2024

Wednesday, 6 November 2024

Ceisteanna (78)

Eoin Ó Broin

Ceist:

78. Deputy Eoin Ó Broin asked the Minister for Education for an update on the large-scale project for a school (details supplied) under the School Building Programme; if a commencement date is available; and if she will make a statement on the matter. [45483/24]

Amharc ar fhreagra

Freagraí scríofa

The large scale capital project at the school referred to by the Deputy is at Architectural Planning Stage 4 - Construction.

Works commenced on site in August 2024 with an estimated contract duration of 36 months.